Construction Gotthard Base Tunnel
gotthard base tunnel diagram, new railway link through alps nrla (green: → excavation direction).
allocation of work
aerial view of erstfeld area (north portal) in 2009
the contracts awarded in sections:
erstfeld (the 7.7 km (4.8 mi) section erstfeld amsteg), 2 tunnel boring machines (tbm) boring 2 tubes. break-through of east tube between erstfeld , amsteg took place on 15 june 2009. portal area surface-mined.
amsteg (the 11.3 km (7.0 mi) section amsteg north of sedrun), arge agn (strabag , züblin murer) received contract work in sector. on 9 december 2009, amsteg section officially delivered owner fitting-out, civil engineering, construction, concrete , lining work completed in 2010.
sedrun (the 8.6 km (5.3 mi) east tube , 8.7 km (5.4 mi) west tube in section north , south of sedrun), along work performed transco (bilfinger se, implenia, frutiger , impresa pizzarotti). final breakthrough in west tube occurred in march 2011. northbound tubes amsteg sedrun multifunction station (north) handed on railway systems contractor transtec gotthard on 15 september 2011, date specified in construction schedule.
faido (13.4 km (8.3 mi) east tube , 13.6 km (8.5 mi) west tube in section south of sedrun faido), consorzio tat (alpine mayreder bau, csc impresa costruzioni, hochtief , implenia , impregilo).
bodio (15.9 km (9.9 mi) east tube , 15.6 km (9.7 mi) west tube in section faido bodio), work performed consorzio tat (alpine mayreder bau, csc impresa costruzioni, hochtief, implenia , impregilo). civil engineering construction, concrete , lining works completed in 2010.
deaths during construction
nine workers lost lives during construction; 1 in amsteg section, 2 in sedrun section, , 3 each in southernmost faido , bodio sections. these were:
on 8 june 2000, worker germany, first victim of tunnel construction, hit boring bar fell down 700 m.
on 12 march 2002, worker south africa buried excavation material.
on 3 april 2003, worker germany hit rock.
on 11 september 2003, worker austria killed being crushed toppling cable drum.
on 21 january 2005, worker italy , switzerland hit colliding mine train.
on 23 november 2006, worker germany crushed death mine train.
on 24 june 2010, worker germany catapulted out of inspection train.
on 16 july 2012, worker italy fell scaffold.
^ status of work . lucerne, switzerland: alptransit gotthard ag. 1 november 2011. retrieved 11 november 2011.
^ overview gotthard base tunnel . lucerne, switzerland: alptransit gotthard ag. 1 january 2012. retrieved 5 february 2012.
^ gotthard base tunnel: driving complete . lucerne, switzerland: alptransit gotthard ag. 23 march 2011. retrieved 16 november 2011.
^ cite error: named reference malins invoked never defined (see page).
^ bundesrat bestätigt vorläufigen verzicht auf die porta alpina . press release, swiss federal authorities. 16 may 2012. retrieved 31 december 2014.
^ final breakthrough of longest railway tunnel in world . lucerne, switzerland: alptransit gotthard ag. 15 october 2010. retrieved 2017-06-05.
^ bedding, james (19 february 2013). switzerland s gotthard base train tunnel redefining europe . telegraph. retrieved 11 april 2013.
^ gotthard base tunnel: driving complete . lucerne, switzerland: alptransit gotthard ag. 23 march 2011.
^ switzerland: first transit in gotthard base tunnel . corridor-rhine-alpine.eu. retrieved 7 december 2016.
^ test trains running on gotthard base tunnel . global rail news. 17 december 2013. retrieved 21 december 2013.
^ construction of century takes shape . lucerne, switzerland: alptransit gotthard ag.
^ celebrations last piece of track laid in record-breaking gotthard rail tunnel | euronews, world news . euronews.com. 31 october 2014. retrieved 25 january 2016.
^ mit 275 sachen durch den gotthard-basistunnel . luzernerzeitung.ch. neue luzerner zeitung. 19 november 2015. retrieved 7 december 2016.
^ projektbeschrieb (in german). agn strabag. 24 september 2010. retrieved 19 october 2010.
^ structurally complete tunnels of amsteg section handed on . lucerne, switzerland: alptransit gotthard ag. 10 december 2009. retrieved 12 november 2011.
^ gotthard approaches final breakthrough, ceneri starts main drive . lucerne, switzerland: alptransit gotthard ag. 31 march 2010. retrieved 12 november 2011.
^ transco sedrun (in german). transco. archived original on 29 may 2010. retrieved 15 october 2010.
^ booth, martina (29 april 2010). gotthard: titanic tunnel . new civil engineer. emap publishing limited. retrieved 15 july 2015.
^ final breakthrough of longest railway tunnel in world . lucerne, switzerland: alptransit gotthard ag. 15 october 2011. retrieved 12 november 2011.
^ installation of railway systems in north has begun . lucerne, switzerland: alptransit gotthard ag. 2 september 2011. retrieved 12 november 2011.
^ st. barbara celebration 2012 (in german). consorzio tat. archived original on 13 september 2012. retrieved 11 april 2013.
^ cite error: named reference memorial invoked never defined (see page).
^ gieri venzin (30 may 2016). andreas reichhardt, † 8. juni 2000 (in german). srf. retrieved 1 june 2016.
^ gieri venzin (30 may 2016). jacques du plooy, † 12. märz 2002 (in german). srf. retrieved 1 june 2016.
^ gieri venzin (30 may 2016). heiko bujack, † 3. april 2003 (in german). srf. retrieved 1 june 2016.
^ gieri venzin (30 may 2016). albert ginzinger, † 11. september 2003 (in german). srf. retrieved 1 june 2016.
^ matthias chapman (12 october 2010). die toten vom gotthard . tages-anzeiger (in german). retrieved 1 june 2016.
^ gieri venzin (30 may 2016). salvatore di benedetto, † 21. januar 2005 (in german). srf. retrieved 1 june 2016.
^ gieri venzin (30 may 2016). andrea astorino, † 21. january 2005 (in german). srf. retrieved 1 june 2016.
^ gieri venzin (30 may 2016). thorsten elsemann, † 23. november 2006 (in german). srf. retrieved 1 june 2016.
^ gieri venzin (30 may 2016). hans gammel, † 24. juni 2010 (in german). srf. retrieved 1 june 2016.
^ gieri venzin (30 may 2016). giuseppe liuzzo, † 16. juni 2012 (in german). srf. retrieved 1 june 2016.
Comments
Post a Comment